Mandi News: बारिश ने फिर रोका पंडोह में निर्माणाधीन पुल का काम, दिसंबर तक पूरा होना मुश्किल

Key Facts Mandi district’s Pandoh area is once again facing delays in the construction of a crucial bridge over the Beas river. The project, which started in October 2025, has been stalled due to rising…

Key Facts

Mandi district's Pandoh area is once again facing delays in the construction of a crucial bridge over the Beas river. The project, which started in October 2025, has been stalled due to rising water levels and strong currents. The piling machine has been removed from the site, bringing work to a halt. The bridge is intended to connect Pandoh market with 12 surrounding panchayats, replacing a previous bridge that was washed away in the 2023 disaster.

Details of the Delay

The construction of the new double-lane steel bridge, 120 meters long, was already delayed earlier due to design changes that caused a two-month stoppage. Now, the monsoon season has added to the woes. Executive Engineer Dushyant Pal of the Public Works Department stated, "Due to strong currents, work has been halted for now. As soon as the water level of the Beas river becomes normal, construction work will be resumed." However, with the target of completing the bridge by December 2026, the timeline appears increasingly difficult.

Impact on Local Residents

Since the old bridge was destroyed in the 2023 floods, residents of 12 panchayats have to travel an extra 8 kilometers to reach Pandoh market. This has severely affected students, working professionals, traders, and daily commuters. Local residents Rohit, Raman, Deep, Tarun, and Jatin expressed their frustration, saying, "If the department had started construction on time as per the approved design, the bridge would have been largely completed by now." They urged authorities to expedite work as soon as weather permits.

What Readers Should Know

The new bridge is being built at a higher elevation than the old one to withstand future floods. Public Works Minister Vikramaditya Singh had inspected the site and set the December deadline. However, with repeated delays, the completion remains uncertain. The department assures that work will resume once the river level normalizes.

FAQ

Why has the Pandoh bridge construction stopped?

Due to rising water levels and strong currents in the Beas river, the piling machine had to be removed from the site, halting work.

When will the bridge be completed?

The target is December 2026, but due to design changes and monsoon delays, it appears challenging.

How many panchayats will benefit from this bridge?

Around 12 panchayats will benefit, serving thousands of residents.

Follow us on Google News

Explore more

Himachal Weather: बारिश-भूस्खलन से 120 सड़कें बंद, दो नेशनल हाईवे ठप; रोहतांग में बर्फबारी

Key Facts Himachal Pradesh is reeling under heavy rain and landslides, disrupting normal life across several districts. As of July 13, 2026,…

More on Himachal from Himachal Pradesh

Wayanad Landslide: हिमाचल के इंजीनियर विक्रम का छह दिन बाद मिला शव

परिचय केरल के वायनाड में हुए विनाशकारी भूस्खलन में लापता हुए हिमाचल प्रदेश के कांगड़ा जिले के इंजीनियर विक्रम का शव छह…

एससी एसटी कॉर्पोरेशन ने चार माह में 220 डिफाल्टरों को जारी किए नोटिस

मुख्य तथ्य हिमाचल प्रदेश अनुसूचित जाति एवं अनुसूचित जनजाति निगम (एससी एसटी कॉर्पोरेशन) ने पिछले चार माह में 220 डिफाल्टरों को राजस्व…

पंचरुखी में 33 केवी सब-स्टेशन का काम जल्द पूरा, बिजली आपूर्ति होगी मजबूत: मंत्री गोमा

मुख्य जानकारी कांगड़ा जिले के पंचरुखी क्षेत्र में बिजली आपूर्ति को और सुदृढ़ बनाने के लिए 33 केवी सब-स्टेशन का निर्माण कार्य…